NANT Y GWYDDON
LANDFILL
RHONDDA, SOUTH WALES
1.0 INTRODUCTION
1.1 Since April 1996 the Environment
Agency, in addition to its normal regulatory actions has conducted specific
studies and contributed to studies by others to quantify odour problems,
investigate alleged health concerns of local communities and impacts on
the local environment. A considerable amount of resources have been utilised
by the Agency in responding proactively to its statutory duties under the
Environmental Protection Act 1990.
2.0 BACKGROUND TO SITE
2.1 The Nant-y-Gwyddon landfill site
became operational in January 1988, being developed and operated by Rhondda
Borough Council (who since 1996 are part of Rhondda Cynon Taff County Borough
Council (RCT) ). The site was designed as an engineered containment landfill
and was built with the aid of two EC grants. At the time of development
there was great local opposition.
2.2 Following legislative requirements
of the Environmental Protection Act 1990 to separate roles of operator
and regulator, a local authority waste disposal company, Rhondda Waste
Disposal Ltd, was formed and a Waste Management Licence was granted under
section 35 of the Environmental Protection Act 1990 by the Rhondda Borough
Council on 15 March 1995. The site is licensed to accept household; non-special
commercial and industrial wastes (192,000 tonnes per year max.). The site
is approximately half full of its total capacity 1.6m tonnes.
3.0 ACTION TAKEN BY THE ENVIRONMENT
AGENCY WALES
3.1 Since April 1996 the Agency has
been carrying out its duty via the following activities:
(i) Site inspections.
(ii) Provision of a 24 hour (freephone
line) incident response service.
(iii) Robust enforcement action.
(iv) Regular liaison with other regulatory
bodies.
(v) Liaison with local community groups
and representatives (RANT).
3.2 In June of 1996 the Agency began
to receive complaints of odour from the site but the odours were transient
and difficult to substantiate and quantify.
3.3 In Autumn 1996 the Agency began
to consider the breakdown of calcium sulphate filter cake as a contributory
cause since under certain conditions this could produce hydrogen sulphide
with its characteristic rotten eggs smell which exacerbated the odour of
landfill gas (LFG).
3.4 In January
1997 the Agency initiated enforcement action by modifying the company's
waste management licence and required the company to carry out three actions:
(ii) A technical
review of landfill gas management within three months.
(ii) A technical
review of leachate management within 3 months.
(iii) The
immediate cessation of deposit of waste containing more than 10% by weight
calcium sulphate.
The company did lodge an appeal with
the Secretary of State for Wales in respect of (iii) above but this was
subsequently withdrawn. The company produced the technical review reports
on LFG but the Agency required further work on the leachate report.
3.5 Concern persisted and a number
of public meetings were held, chaired by the local MP Allan Rogers to examine
fears of the local community regarding the potential health effects from
the site. The Agency actively participated in these meetings and responded
positively wherever possible to the concerns raised. The
main health concern focused on the unknown levels of LFG being emitted
from the site .The Agency responded by agreeing to commission consultants
to carry out a comprehensive study and Rhondda Cynon Taff County Borough
Council agreed to commission a health study.
3.6 In June
1997, the Agency commissioned Entec, a firm of specialist environmental
consultants to carry out the following work:
(i) Analyse
the composition of raw LFG in the body of the site from existing boreholes
and wells
(ii) Critically
appraise the LFG controls and management practices.
(iii) Monitor
the air quality of the atmosphere within the boundary of the site.
(iv) Monitor
the air quality in the surrounding communities.
(v) Assess
the findings in respect of health and annoyance reference levels
(vi) Carry
out modelling of LFG emissions.
(vii) Make
recommendations for site improvements.
3.7 In July
1997 a demonstration by the local protest group RANT (Rhondda Against Nant-y-Gwyddon
Tip), caused the company to withdraw site personnel. This meant that apart
from site security staff no one attended the site on a regular basis to
operate and maintain the LFG and leachate control equipment. The Agency
decided the situation was serious and took the matter to the High Court,
using for the first time a provision under section 6 of the Environment
Act 1995. The High Court found in favour of the Agency on the 25 July and
issued an Injunction against the Directors of the company that required
them to maintain the LFG and leachate equipment. The company met the requirements
of the Injunction and company personnel returned to the site.
3.8 In January 1998 the Agency received the final version of the
Entec report, which found that levels of hydrogen sulphide within the site
were substantially above those normally found in landfill sites elsewhere
in the UK. Transient
plumes of emissions of hydrogen sulphide into the surrounding communities
were found above W.H.O annoyance levels but well below any reference levels
for known health effects. The report made a number of recommendations for
the alleviation of the odour and leachate problems .The Agency immediately
placed the report on the public register and distributed copies to all
interested parties. A public meeting was also held to discuss the findings
with the local communities in addition to meetings with the operator, Rhondda
Cynon Taff County Borough Council, Bro Taf Health Authority and RANT.
Although there were criticisms over the time taken for the consultants
to produce the report there was very little disagreement on the findings
from the operator.
3.9 On the 8 May 1998 the Agency imposed
a major modification to the licence requiring the company to undertake
a number of works to solve odour and leachate problems at the site as a
matter of urgency, namely:
A) Cap the existing tipped area with
an impermeable gas barrier;
B) Design, construct and maintain
a landfill gas management and control system at the site to ensure that
all gas generated at the site is collected and burnt in a high-temperature
flare in order to destroy any odorous components, and minimise any combustion
by-products.
C) Continuously and accurately monitor
the atmosphere within the site boundary and at three points in the community
for hydrogen sulphide and sulphur dioxide.
D) Keep records of wind/speed and direction,
temperature, rainfall, atmospheric pressure and relative humidity.
E) Procure financial provision to
discharge the above obligations relating to air quality monitoring.
F) Carry out works to the leachate
management system.
G) Undertake a risk assessment of
the existing un-tipped lined area of the site (Phase 2) to demonstrate
its suitability for accepting further waste deposits. No wastes to be deposited
there until this risk assessment has been undertaken and any defects remedied.
The compliance period for the works
required by the Notice was 6 months from date of service.
3.10 The company responded to the modification
by threatening, in late May 1998, to close the site and commence winding
up the company unless Rhondda Cynon Taff County Borough Council, the owners
of the company, provided additional funds. At the end of June 1998, the
company secured the necessary funding from Rhondda Cynon Taff County Borough
Council to enable them to undertake the works. The total cost of the works
was estimated to be £1.6 m. Rhondda Cynon Taff County Borough Council
provided share capital of £1.1m and £500,000 was found from
the company.
3.11 In late October 1998 progress
on site indicated that the Agency's deadline of November would not be met
in full but would be met by mid December weather permitting. The company
was also seeking alternative approaches from the Agency on the matter of
air quality monitoring but did not wish to appeal against the modification
notice.
A meeting was then held with the company
on the 11 November at which progress against the third modification was
reviewed. The position was :-
(i) Ten modification conditions had
been met.
(ii) Two had not been completed -
site capping and air quality monitoring.
(ii) One (relating to the need for
a risk assessment on the un-tipped area) was agreed to be deferred.
Whilst recognising the company's efforts
the Agency was very concerned that the principal recommendation to cap
the site had not been completed. The Agency also reaffirmed the need for
the air quality monitoring and advised the company that if they had difficulties
accepting this to lodge an appeal before the expiry of the statutory period
.
3.12 It became
apparent to the Agency that the capping methodology chosen by the company
was seriously flawed and the deadline of mid-December could not be met.
Consequently the Agency decided to prosecute the company for failing to
comply with the modification condition relating to capping the site and
also served a further enforcement Notice requiring the completion of the
cap by March 1999 and the submission of an air quality monitoring programme
by February 1999.
3.13 Just prior to Christmas 1998 the
company lodged a petition in the High Court to seek an Administration Order
and wrote to the Welsh Office requesting them to hear a late appeal against
the majority of the Agency's modification conditions imposed in May 1998.
The Agency was extremely concerned that these developments would delay
completion of the works and took the decision to intervene in the hearing
for the Administration Order.
3.14 Between January and September
1999 the Agency made strenuous efforts to ensure the site's environmental
impact was minimised by the Administrator and made robust representations
in the High Court to ensure the Agency's concerns were understood.
3.15 Unfortunately the Administrator
raised a legal challenge as to the ability of the Agency to take proceedings
against a company subject to an Administration Order without the approval
of the High Court. The Agency challenged this claim. Although losing an
Appeal to the High Court, the Agency won an Appeal at the Court of Justices
in February 2000. Subsequently on the 27th March 2000 Rhondda Waste Disposal
Ltd were found guilty of an offence under the Environmental Protection
Act 1990 for failing to complete the outstanding capping works. The company
was fined £20,000 and costs of £11,365 were awarded to the
Agency.
3.16 On 22 September 1999 the Agency
formally transferred the waste management licence from Rhondda Waste Disposal
Ltd to Amgen Rhondda Ltd. Amgen Rhondda Ltd, is a subsidiary of Cynon Valley
Waste Disposal Company Ltd., which is another LAWDC owned by Rhondda Cynon
Taff County Borough Council. Rhondda Cynon Taff County Borough Council
have provided a further capital injection of £900k to enable Amgen
Rhondda Ltd to commence the outstanding works.
3.17 Amgen Rhondda Ltd has undertaken
a programme of works at the site to prevent the site causing odour annoyance
and improve leachate controls. The following actions have been undertaken
by the company
(i) Air Quality Monitoring Programme
commenced March 2000
(ii) Leachate Pipeline Renewal completed
August 2000
(iii) Permanent and Intermediate capping
of the site programmed to be completed by October 2000
4.0 WORK WITH OTHER BODIES
4.1 The Agency
recognises that whilst it has a statutory duty to ensure waste management
licensed sites do not cause pollution of the environment, harm to human
health or serious detriment to the local amenity, other regulatory bodies
have legitimate interest in the site. The Agency has worked closely with
the following in a partnership approach:-
- Environmental
Health - Rhondda Cynon Taff County Borough Council, in respect of their
statutory nuisance and air quality responsibilities.
- HSE - in
respect of the occupational health aspects.
- Bro Taf
Health Authority - who have the lead responsibilities for determining public
health priorities. The Agency has contributed information to various health
studies commissioned by Bro Taf Health Authority, e.g. Professor S Palmer,
Combined Centre for Public Health, University of Wales, College of Medicine.
4.2 Whilst
there has been no causal link established by any of the health studies,
several recommendations have been taken forward as part of the recently
announced ill health and landfill research programme which is jointly funded
by Dept. of Health, DETR, National Assembly for Wales and MAFF. The Agency
will contribute to these studies at Area, Regional and National levels.
4.3 The challenges presented by the
wastes generated in our society cannot be underestimated. Any potential
risks to health from landfills today must be assessed alongside other risks,
often well known and greater in effect, as well as considering what improvements
have been made over the past few decades. At present there are no available
alternatives for waste disposal in SE Wales. However, whilst the Agency
is committed to ensuring that it is a robust yet fair regulator it is actively
promoting more sustainable waste management practices amongst all sectors
of communities which will hopefully result in a reduced reliance upon landfill
within time scales set by the anticipated EU Landfill Directive. |